S-34.1, r. 2 - Regulation respecting petroleum exploration, production and storage on land

Full text
144. If a surface casing is installed, the authorization holder must ensure that it is inserted in a competent formation at a depth allowing for a sufficient anchoring of the well blowout preventer, ensures the control of anticipated pressures in the well and is equipped with an opening valve.
O.C. 1252-2018, s. 144.
In force: 2018-09-20
144. If a surface casing is installed, the authorization holder must ensure that it is inserted in a competent formation at a depth allowing for a sufficient anchoring of the well blowout preventer, ensures the control of anticipated pressures in the well and is equipped with an opening valve.
O.C. 1252-2018, s. 144.